General Moly Updates Mt. Hope Permitting Progress

LAKEWOOD, CO - General Moly Inc. reported a permitting progress update on Mt. Hope and reiterated its current expectation to receive all required permits by mid-2009.
Bruce D. Hansen, Chief Executive Officer, said, "We continue to execute against our permitting timeline and have filed applications for the key Nevada State permits. Although we recognize that we do not fully control the ultimate timing, our technical data for the EIS continues to be submitted in a timely manner, and we continue to expect all the key Nevada State issued permits will be received no later than Q1 2009 and the final EIS Record of Decision in mid-2009.
"Our plans call for environmental protections that are intended to be at the leading edge of mining industry environmental efforts. Our goal is to build a facility that will stand out as a model in the industry."
A Class II Air Quality Control Permit (air permit) application was submitted to the Nevada Division of Environmental Protection (NDEP) on July 11th. The air permit regulates air emissions associated with mine and processing operations. The air permit must be acquired prior to the start of construction for any facility that generates air emissions, including the processing plant and roaster. The Mt. Hope project qualifies for a Class II permit because anticipated emissions for each of the criteria pollutants will be less than the significance level of 100 tons per year. Criteria pollutants of importance to the project include particulate matter and sulfur dioxide. The Mt. Hope project will incorporate leading-edge technology and practices for the control of air emissions. The Company expects receipt of this permit by the first quarter of 2009.
A Water Pollution Control Permit (WPCP) application was also submitted to the NDEP on July 11th. The WPCP regulates the management of process fluids to prevent impacts to surface and ground water. The WPCP requires that mine facilities be managed for zero discharge. The Mt. Hope design incorporates elements such as a fully lined tailing facility, a full stormwater capture system for the processing area and innovative closure plans; all of which exceed regulatory standards. The Company expects receipt of this permit by the first quarter of 2009.
A permit application for a Dam Safety Permit was submitted to the Nevada Division of Water Resources on July 28th for the tailing facility. The Dam Safety permit regulates the construction and operation of the tailing dam to ensure stability and public safety. The Company expects receipt of this permit by the end of the year.
The company's address is 1726 Cole Blvd., Suite 115, Lakewood, CO 80401, (303) 928-8599, Fax:(303) 928-8598.