Greenstone Project Is Currently 96% Complete

VANCOUVER - Equinox Gold Corp. reported on construction and commissioning progress at its Greenstone Project in Ontario, Canada. The Greenstone Project is being developed as a 60/40 partnership, respectively, by Equinox Gold and Orion Mine Finance Group, and will be one of the largest gold mines in Canada, with average annual gold production of more than 400,000 ounces over the first five years and more than five million ounces of gold produced over its initial 14-year mine life.

The Greenstone Project is 96% complete. Pre-commissioning1 activities are ongoing in most of the main process plant areas, including the crushing and grinding circuits, and wet commissioning1 is underway in select areas. The Project remains on track for a total spend of $1,225 million. At September 30, 2023, $1,087 million (89%) of the budget had been spent (100% basis).

The realigned 4.7 km of Highway 11 was opened to traffic in August and the power plant was turned over to the operations team in September, both ahead of plan. The permanent effluent water treatment plant, truck shop, warehouse, sewage treatment plant, potable water treatment plant, pit and plant site fuel stations, reagent storage, site mixed emulsion (explosives) plant and natural gas pipeline to site were previously turned over and are all in operation. All major equipment is now on site and construction is 96% complete. The focus is on remaining electrical and instrumentation installations in the process plant. In October, the tailings storage facility ("TSF") was completed to planned elevation. Commissioning of the TSF is on track for December 2023.

Pre-commissioning activities are ramping up in coordination with final construction activities, with systems checks underway at the crusher, ball mills, ore storage dome and high-pressure grinding rolls ("HPGR") areas. Wet commissioning has commenced at the leach tanks and in the crusher area. The third Epiroc Pit Viper 235 drill has been commissioned. Commissioning of CAT 793F haul trucks 9 and 10 is underway, and haul trucks 11 to 14 and the LeTourneau 1850 loader will be ready for service in early Q1 2024. More than 15 million tonnes of material has been moved to date and build-up of the ore stockpile is ahead of plan and on track to exceed the 800,000 tonnes start-up target.

Operational readiness activities and hiring are progressing in-line with plan. An update on Greenstone 2024 operating costs and production estimates will be reported in connection with the Company's annual production and cost guidance in Q1 2024.

Greg Smith, President & CEO, said, "With the Greenstone Project 96% complete and the power plant fully operational, the priority is now on completion and commissioning of the process plant, commissioning of the TSF and ramp up of mining and operations. The project continues to advance on budget and on schedule. We look forward to pouring gold in the first half of 2024 and then achieving commercial production."