Production Update For Jerritt Canyon

VANCOUVER, BC - Yukon-Nevada Gold Corp. reported production update for the third quarter and progress on the winterization of the milling facility at Jerritt Canyon located 50 miles north of Elko, Nevada. Jerritt Canyon is operated by Queenstake Resources USA Ltd., a wholly owned subsidiary of Yukon-Nevada Gold Corp.

The Jerritt Canyon operation shipped 21,345 ounces of gold in Q3, comprised of 6,865 ounces in July, 7,195 ounces in August and 7,285 ounces in September.

Winterization and improvements of the milling facility at Jerritt Canyon are well underway and include installation of a new ore dryer, rebuilding the crushing circuit, construction of housing for the ore dryer, fine-crushing circuit conveyor reconfiguration, change-out of the Merrill-Crowe precipitation circuit with an electrowinning circuit, replacement of a quench tank, and improvements to the oxygen plant.

It is anticipated that all winterization and improvement projects will be completed by mid-December. Manufacturing of the new ore dryer encountered some delays, but shipping from the manufacturer started on October 25, 2011 and will be at site by mid-November 2011 and fully installed by mid-December, 2011. The fine crushing circuit is being rebuilt and will be fully enclosed from weather and fully operable by mid-December. The operation has continued to produce gold through the current construction by implementing work-arounds to the refurbishment activities. A shutdown period of around 10 days will be required, likely starting in late November.

Work on the new tailings storage facility ("TSF") is also progressing on schedule and on budget. In July 2011 the Company received regulatory approval to break ground and start construction of the new TSF. This new TSF will be state of art using two double lined impoundments: one for tailings solids and one into which tailings water will be decanted. This separation during operations is intended to provide greater stability to the tailings and reduce the time and costs for the ultimate closure and reclamation of the facilities. The TSF is also expandable and will be able to serve Jerritt Canyon many years into the future.

Earthworks on TSF water storage reservoirs are complete and installation of the double lining, piping and pumping systems is in progress. Installation of the double lining on the first water storage reservoir will be complete and work continues on double lining the second water storage reservoir. Earthworks on TSF are 95% complete and will be completed by the end of the month. Installation of the double lining, piping and pumping systems will be completed by August 2012 allowing use any time after when the first TSF reaches maximum capacity.

Chief Operating Officer, Randy Reichert states, "We are in a good position to ramp up production at the milling facility now that mining has begun at the SSX-Steer underground mine and once the refurbishments are completed at the mill. We are confident that everything should be running smoothly going forward into the winter months at Jerritt Canyon. Our team worked long and hard to have everything finished before the winter sets in. With many years of experience developing and operating mines in arctic environments, I am confident that all refurbishment projects will be completed as planned even if winter sets in early."